Campus Center timeline

Issue date: 1/7/08 Section: CampusCenter
  • Print
  • Email
  • Page 1 of 1
The Campus Center under construction in December, 2007.
Media Credit: Marcos Dominguez
The Campus Center under construction in December, 2007.

2000 Initial planning

2001 University approval of project

2002 State approval of project

2003 Selection of architect (Smith Group and Ratio)

2003-2005 Project design

July 27, 2005 - Construction contract awarded to Hunt Construction

Aug. 8, 2005 - Site demolition begins

Sept. 30, 2005 - Groundbreaking ceremony

June 16, 2006 - Dan Maxwell appointed Campus Center director; begins job July 1, 2006

Jan. 20, 2007 - Installation of the bell tower

June 26, 2007 - Announcement of names project for interior spaces in the Campus Center

Dec. 17, 2007 (tentative) - Soft opening, doors open to public/limited access

Jan. 8, 2008 (tentative) - Completion/food court open to public

April 9, 2008 (firm) - Campus Center building dedication
Page 1 of 1

Article Tools

Be the first to comment on this story

  • NOTE: Email address will not be published

Type your comment below (html not allowed)

  I understand posting spam or other comments that are unrelated to this article will cause my comment to be flagged for deletion and possibly cause my IP address to be permanently banned from this server.

Advertisement

Poll

Do you believe Senator Obama will deliver on his promise of change?
Submit Vote

View Results

Links

Advertisement